Division 6 (Bassano) - TA Excavating has completed the installation of the lines and structures in this area. Currently the pipes are being pressurized and tested for leaks. Once this process is complete the contractor will disinfect and flush the lines prior to the County taking over operation. It is expected that these lines will be put into service in the early spring. Landowners that are part of this project should watch the mail for a letter from the County telling them they are allowed to pick up their flow emitter assembly and connect to the system.

Division 9 (Gem) - K-Line Maintenance and Construction are working their way north past the hamlet of Gem performing the installation of pipe and structures for this project. This system is expected to be put into service in the fall of 2016. Landowners that are part of this project should watch the mail for a letter from the County telling them they are allowed to pick up their flow emitter assembly and connect to the system.

Booster Stations - Parcon Construction is wrapping up the construction of 3 booster stations which will increase the pressure in the division 6 and division 9 distribution lines to facilitate water reaching the north end of the County. These stations will be completed and in service under a timeline that will not affect the commissioning of the two projects affected.