The County of Newell has awarded Contract 1 of the County of Newell Water Project Phase 2 to Syncore Directional Drilling from Coalhurst.  Syncore is a qualified contractor that has worked with the County in the past, and is fully capable of completing the assignment. 

This project includes the servicing of 126 locations via the installation of 20 kilometers of High Density Polyethylene pipe.  This contract has a substantial completion date of May 19, 2023, and the project area is identified in the image below:


The County of Newell is currently working on organizing the composition of future contracts.  It is expected that Contract 2 will be issued for tender later this winter, and an additional 2 contracts will be released next summer/fall.  The 440 locations registered are expected to be serviced by the spring of 2024.  Updates will be posted here as they become available.